Friday, March 18, 2011

Progress.

I dropped the final construction plans back to Wisdom yesterday with one question in mind "So when will we see some work starting?"
The reply to this was "The excavation should start within 3-4 weeks, followed by the slab 1-2 weeks after that". This is good news but as always taken with a grain of salt. Lets hope the weather is favorable so we get very few or no delays.

Our plans come back from Sydney Water with no conditions so its full steam ahead!

Friday, February 18, 2011

We have the first Approval!!

We have been hanging on the council website and also the regular updates from Wisdom about our DA. The first part of it has been Consent Approved, hopefully without conditions. We now wait for the other services ie. Sydney Water and then we wait for the Construction Certificate to be issued.


We have also been trying to get all the loose ends and final touches done to everything now so (hopefully) nothing pops up during the build. Wisdom are probably sick of me now as I have been in contact with them at least three times a week over the last 3-4 weeks. Thankfully we are nearly there.

Wednesday, February 2, 2011

DA Update

We have been advised that we now have a DA Number and a street number. We now play the waiting game.

Saturday, January 22, 2011

Good News!

Received a phone call from Wisdom saying that there will not have to be any changes to our plans YAY!! (as previously mentioned in our post about Plans being lodged with council take 2.
The architects picked up a simple mistake in the calculations shown on the drawings. We actually don't know what landscape percentage we are at, at the moment but at least we are over 50% and the plans have been returned to council (with bushfire assessment attached) to keep things moving forward.

And then there was light

Met with Wisdom today to finalise our electrical plan. We originally allowed an additional $500 in the tender for extra power points, light fittings, etc.Thankfully after all the additions that we made we came in just under the $500.

Here is our final electrical plan.


On a side note we visited our block today and the construction fence has finally been removed. We were able for the first time to walk onto our block (officially) and even park in our own driveway.

Wednesday, November 17, 2010

Land Registration and Working Drawings

We have (finally) received notification of our land being registered and settlement at this stage is set for 6th December. This took a total of 53 days when it should have only taken 10. At least now we can relax on that front.

We also received the working drawings for our house and we have approved these which allows the final stages of the tender to be prepared, including the building contract.

It shouldn't be to long now until we have to finalise the colour selection process.







Wednesday, October 20, 2010

Waiting

We are currently waiting for the Land to settle. The plans are currently with council for registration/approval. This process is supposed to take 10 days. We are currently at 25 days.

The other thing we are waiting on is the final drawings of our home. Exciting times!!