Thursday, July 28, 2011

Photos and tentative handover

Seeing that we got to go inside today I took the chance to grab a few pics.

Our handover has been booked for August 10th and our SS has confidence that this will happen, as long as all other parties play along.

Here are the pics:




Kitchen Splash back




Wet areas


Linen/Media Cupboard


Leisure Room Media alcove


Home theater cabling


Garage door motor

Sunday, July 24, 2011

Weekly Photo - Week 19

Weekly Progress Photo 17/07/2011

Changes: Tiling almost complete, home theater Cabling started, electrical completed, more fittings installed, door furniture installed, kitchen splashback done, down pipes installed

Friday, July 15, 2011

One Big update!!

Due to a few things happening at the moment, here is one big update to cover quite a few things that have happened over the last week or so.

Water Tank and down pipes installed


 

Door Furniture installed.




Wet Area fittings installed







 Electrical and Kitchen Splash Back done.







Monday, July 4, 2011

Tiling underway

Whilst the Painters finish the other areas of the house, the tiler has been in and laid some tiles! I am very happy with the tiles we have chosen. Our Laundry tub was also installed. We were unable to get photos of the en suite as the tiler was still hard at it.







Weekly Photo - Week 17

Week 17 Progress Photo 03/07/2011
Changes: Painting Continues, Tiling started, More minor electrical work, Laundry tub installed.