External Plumbing

All of the plumbing has been done for the downpipes, and a temporary water point has been put in.






Monday, April 11, 2011

Slabbed!

Our slab has been poured and doesn't it look good. Next step Frame and Windows!!

Home Theater & Garage

 Water tank Slab & Kitchen

Lesuire Room & Alfresco 

 Bedroom 4 & Laundry 

 Toilet & Bathroom 

Bedroom 2, Study/Bedroom 4 and Ensuite 

Master Bedroom & Front Porch 

The Slab & Side of the Slab

Sunday, April 10, 2011

Weekly Photo - Week 5

Week 5 Progress Photo 10/04/2011
Changes: Slab form work, waffle pods, plumbing, minor electrical

Tiles and Carpet Selection

Saturday seen us head over to Di Lorenzo to make our carpet and tile selection. This is what we chose:

Carpet: Victoria Carpet
Colour: Savino forte 50% wool/50% Nylon Blend


Main Living Tiles: Cocoa Smooth



Front Porch/Step Tiles - Cocoa


Wet Area Floor Tiles: 2Brech/Smooth Grey


Wet Area Wall Tiles: Polatino White Gloss


Feature Tile strip - Mosaic #109


Thursday, April 7, 2011

Pre Slab

All of the Waffle Pods and Rio Mesh have been put in place ready for the slab to be poured. Maybe we will have a slab by Friday











SS, Waffle Pods, Mesh and Plumbing

Wednesdays visit seen more progress on the slab work. We had delivery of the Waffle Pods and Rio Mesh and work has been done on the plumbing.

We have also had what I believe to be an earth cable show up.

We also received a phone call from our SS (J) introducing himself and advising of the progress and that he will be ordering the frame shortly. He said we should have a slab by the end of the week but I reckon early next week as the weather hasn't exactly been on our side.