Sunday, May 1, 2011

Weekly Photo - Week 8

Week 8 Progress Photo 01/05/2011
Changes: Windows Installed, Plumbing installed, Bricks, Sand and cement delivered.

Friday, April 15, 2011

Little annoying things

Now I'm sure a few more of these little annoying things will pop up throughout the build, but I wasn't expecting them to start so early on in the piece.

I visited our site today to find someone has started to use our site as a dumping ground for builders waste. This tiling waste has shown up in the last 24 hours dumped in our driveway.





I also noticed that when the external plumbing was done they have damaged our slab in the alfresco area. They attempted to repair it but done a pretty crappy job.




We weren't planning on tiling this for a little while so I hope they fix it properly. I have passed it on to Wisdom, let's hope they can fix it, as it really stands out makes the area look bad.


- Posted using BlogPress from my iPad

Monday, April 11, 2011

Slabbed!

Our slab has been poured and doesn't it look good. Next step Frame and Windows!!

Home Theater & Garage

 Water tank Slab & Kitchen

Lesuire Room & Alfresco 

 Bedroom 4 & Laundry 

 Toilet & Bathroom 

Bedroom 2, Study/Bedroom 4 and Ensuite 

Master Bedroom & Front Porch 

The Slab & Side of the Slab

Sunday, April 10, 2011

Weekly Photo - Week 5

Week 5 Progress Photo 10/04/2011
Changes: Slab form work, waffle pods, plumbing, minor electrical

Thursday, April 7, 2011

Pre Slab

All of the Waffle Pods and Rio Mesh have been put in place ready for the slab to be poured. Maybe we will have a slab by Friday











SS, Waffle Pods, Mesh and Plumbing

Wednesdays visit seen more progress on the slab work. We had delivery of the Waffle Pods and Rio Mesh and work has been done on the plumbing.

We have also had what I believe to be an earth cable show up.

We also received a phone call from our SS (J) introducing himself and advising of the progress and that he will be ordering the frame shortly. He said we should have a slab by the end of the week but I reckon early next week as the weather hasn't exactly been on our side.












Slab Formwork and Piering

Its come to the stage of daily visits to the site and so far something different has happened every day. We know it wont be this way all the time but its good to see.

On Tuesday I dropped by and we had our peiring and slab layout/formwork.