Thursday, April 7, 2011

Pre Slab

All of the Waffle Pods and Rio Mesh have been put in place ready for the slab to be poured. Maybe we will have a slab by Friday











SS, Waffle Pods, Mesh and Plumbing

Wednesdays visit seen more progress on the slab work. We had delivery of the Waffle Pods and Rio Mesh and work has been done on the plumbing.

We have also had what I believe to be an earth cable show up.

We also received a phone call from our SS (J) introducing himself and advising of the progress and that he will be ordering the frame shortly. He said we should have a slab by the end of the week but I reckon early next week as the weather hasn't exactly been on our side.












Slab Formwork and Piering

Its come to the stage of daily visits to the site and so far something different has happened every day. We know it wont be this way all the time but its good to see.

On Tuesday I dropped by and we had our peiring and slab layout/formwork.